Our Lady Sacred Heart, Kensington

The $5M new school hall for Our Lady of the Sacred Heart College, Kensington, comprised of a new hall and associated facilities with a roof top entertainment area.

Northrop worked with Reitsma Construction and JDH Architects through the Design and Construct phase to rationalise the proposed excavation and footing design.

By implementing an alternative footing design using screw piles in the sandy strata, Northrop achieved significant cost savings, enabling a competitive Design and Construct bid.  

OLSH Kensington
Client Name
Reitsma Constructions
Construction Value
$5 million